Enter your move-in date and a few facts about the new space. You get a dated plan of who does what and when, what is already late, and how much cabling, Wi-Fi and rack space the office needs. Free, no sign-up.
More about the move (optional, makes the plan sharper)
Who does what, week by week
- Late
- Due now
- Coming up
- Done
- Provider lead time
- Select any bar for details
Every step
Network estimate
Send this plan to Cablify
We look at your dates and drop count, then book a free site survey, usually within 1 to 2 business days. Your plan link is already in the message, so we see exactly what you see.
- Commercial data cabling, fibre, Wi-Fi, racks, cameras and door access across the GTA
- Every drop Fluke tested before you move in
- Our own employed technicians, 7 days a week from 7 am to 8 pm
Rather talk it through? Call 647-846-1925 or email sales@cablify.ca.
Your plan is added to the message below. Add anything else we should know.
How the planner sets your dates
The planner works backward from your move-in date. Every step has a typical lead time for a GTA office move, and each bar shows when that step should start and when it needs to be finished. A step that should already have started turns red and restarts at today, so the board always shows what to do next.
| Step | When it is scheduled | Why that much time |
|---|---|---|
| Internet, provider already in the building | Ordered 60 days before move-in | Installs in a building the provider already serves often take about four weeks. A missed appointment or a building access problem can add two more. |
| Internet, not sure yet | Ordered 90 days before | Until the provider checks your suite, you do not know if it is a quick install or a construction job. |
| Internet, new fibre build | Ordered 150 days before | New fibre into a building needs permits and construction, which can run three to six months or longer. |
| Landlord drawing review | Sent about 80 days before, approved by 60 | Downtown towers aim to review in about two weeks and can take up to a month, plus time for changes. |
| Phone number port | Started 30 days before | Ports usually take 5 to 10 business days once accepted, and a rejected port starts over. |
| Comms room power | 45 to 35 days before | A licensed electrical contractor files with ESA, and buildings may want two weeks of notice for a shutdown. |
| Cabling installed | Finished 21 days before | Leaves three weeks to test every drop, mount Wi-Fi and set up the network before people arrive. |
Internet lead times are planning estimates, not provider promises. Canadian carriers do not publish business install times, so ask for your install date in writing. For larger offices (more than 250 drops, 25,000 sq ft or three floors) the early steps start three weeks sooner. A bare space being built out adds two weeks of landlord review and a rough-in step before the ceilings close.
How the network estimate works
- Data drops: 2 per desk, which is the TIA minimum for a work area, plus 3 per meeting room, 2 per Wi-Fi access point, 1 per printer, 4 per floor for reception, the kitchen and wall displays, 1 per camera and 1 per card-access door. Then 10% spare for the changes that always come. Our guide to network drops per room goes room by room.
- Wi-Fi access points: 1 for every 1,500 sq ft, or enough to carry about 2.5 devices per person at 40 devices per access point, whichever is higher. Walls, glass and ceiling height change the real number, and a Wi-Fi survey confirms it.
- Comms rooms: at least one per floor, and another when a floor is over about 10,000 sq ft or a cable run would pass 90 m.
- Rack: 1U for each 24-port patch panel plus 1U for its cable manager, 1U per 48-port switch, then a firewall, the provider equipment, a UPS and a power bar, with a quarter of the rack left free for growth. The rack unit chart shows the sizes.
- Power and heat: PoE power for access points, phones and cameras plus the switches, turned into a UPS size and a heat load (watts × 3.41 = BTU per hour). The PoE power calculator goes deeper on the switch budget.
Ontario details that catch office moves out
Building air shuts off at night. Many Toronto towers run base-building air conditioning only in business hours. One downtown tower lists weekdays 8 am to 6 pm and Saturdays 9 am to 5 pm. A comms room runs all the time, so it needs its own cooling, and that needs landlord approval.
Plenum ceilings need FT6 cable. Under the National and Ontario building codes, data cable exposed in a return-air plenum must be FT6 rated. Some downtown towers ask for FT6 on every horizontal and riser run, plenum or not.
Rack power is electrical work. In Ontario you can only hire a Licensed Electrical Contractor for electrical work, and an ESA notification is almost always needed. Cablify arranges this through a licensed electrical contractor so power and data land on the same schedule.
Your old cabling can follow you. Office leases often require you to remove your cabling when you leave, and some buildings charge the last tenant for abandoned cable. Read the restoration clause in your old lease early.
VoIP 9-1-1 uses your registered address. Update the 9-1-1 address for every VoIP line on move-in day so an emergency call goes to the new suite, not the old one.
Office move IT checklist
The same plan as a plain list, for a typical move where the internet provider is not confirmed yet. Use the planner above to get your own dates.
4 to 5 months before move-in
- Check which internet providers serve the building and confirm service for your suite.
- Get the building rules for tenant work, approved contractors and insurance.
- Pick the comms room location.
3 months before
- Order the internet circuit.
- Book a cabling site survey and get the drop map and quote.
- Send the cabling and power drawings to the landlord.
2 months before
- Approve the cabling plan, then order switches, firewall and access points.
- Arrange 24/7 cooling for the comms room.
- Read your old lease for cabling removal.
4 to 6 weeks before
- Dedicated circuits for the rack, by a licensed electrical contractor.
- Book the freight elevator, riser access and after-hours work.
- Start the phone number port.
- Pull, terminate and label the cabling.
2 to 4 weeks before
- Internet installed and extended to your suite.
- Fluke test every drop and mount the Wi-Fi access points.
- Set up backup internet for move week.
- Give notice on the old lines.
The last two weeks
- Set up switches, firewall and Wi-Fi, then test everything end to end.
- Brief staff on what to unplug and who to call.
- On move-in day, update the VoIP 9-1-1 address and patch the desks.
After the move
- Return provider equipment and close old accounts.
- Remove old cabling if the lease requires it.
For the design side of a new office, see the new office network cabling plan, or talk to us about data cabling in Toronto.
Office move IT questions
How far ahead should we order internet for a new office in Toronto?
Order it as soon as the lease is signed. Plan on about 60 days when a provider already serves the building, 90 days when you are not sure, and five months or more when the provider has to bring new fibre into the building. These are planning estimates, so get the install date in writing and line up LTE or 5G backup in case it slips.
How many network drops do we need per employee?
Plan on two drops per desk, which is the TIA minimum for a work area. Meeting rooms, Wi-Fi access points, printers, reception and spare capacity add more, so most offices end up close to three drops per person. The planner shows the breakdown for your headcount.
How many Wi-Fi access points does an office need?
A common starting point is one access point for every 1,500 sq ft, checked against a device load of about 2.5 devices per person. Walls, glass, ceiling height and how many people sit in one area change the real number, so a Wi-Fi survey sets the final count and placement.
What size network rack does a small office need?
It depends on the drop count. Up to about 20 drops usually fits a 12U wall-mount rack, and up to about 95 fits an 18U or 24U rack. Past that, with a UPS and room to grow, a 42U floor rack is the usual choice. The planner sizes the rack from your patch panels, switches and core equipment and leaves a quarter of it free.
Does the comms room need its own electrical circuit?
Yes. A typical office rack needs two dedicated 20 A, 120 V circuits, and a larger UPS may need a 30 A circuit. In Ontario that work has to be done by a Licensed Electrical Contractor with an ESA notification. Cablify can arrange one so the power is ready before the network goes in.
Do we have to remove our old cabling when we move out?
Check the restoration clause in your lease. Many office leases require tenants to remove their cabling at the end of the term, and some buildings bill the last tenant for abandoned cable left in the ceiling. Booking removal as part of the move avoids a surprise charge after you leave.
How long does it take to port our business phone numbers?
Once the port request is accepted, it usually takes 5 to 10 business days. Start about four weeks before move-in, because a port is rejected if the business name, address or account number does not match the old provider’s records exactly, and a rejection starts the clock again.
Can we reuse the cabling already in the new space?
Sometimes. Existing cable is only worth keeping if it is the right category, reaches where your desks will be, and passes a certification test. Choose “Has cabling we want to reuse” in the planner and it adds a test step before the design is finished.
Related tools and guides
- New office cabling planStep-by-step design guide for a new office network.
- Network drops per roomHow many drops each room type needs.
- Rack unit chartRack heights, depths and what fits in each.
- PoE power calculatorSwitch power budget, watts and distance.
- Conduit fill calculatorHow many data cables fit in a conduit.
- Data cabling in TorontoOffice cabling, moves and fit-outs across the GTA.