Cabling subcontractor on a high-capacity Mississauga data centre. Floor maps and digital plans signed off before a single cable was pulled, then fiber and Cat6 to the drawing.

Project Description

We were brought in as the cabling subcontractor on a high-capacity data centre near Highway 401 and Mississauga Road, working for the IT company that held the contract.

SiteHigh-capacity data centre, Mississauga
Our roleCabling subcontractor to the IT prime
ScopeDesign, floor maps, fiber and Cat6 for the whole facility
DeliverablesDigital plans, labelling scheme, test results, as-builts
TeamCabling crew, design, project management
StandardsStructured cabling practice and full documentation

Why data centre cabling is a different job

In an office, a bad cable run is an inconvenience. In a data centre it is a cooling problem, a capacity problem and an outage waiting for a maintenance window. Bundles routed across the wrong path block airflow through the cabinets. Unlabelled patching means nobody will touch a suspect cable during an incident because they cannot prove what it feeds.

So the drawing work matters as much as the install. We did the design before anyone pulled a single cable.

Phase one: survey the room as it is

  • Walked the physical layout, including cabinet rows, containment and where the existing pathways actually ran rather than where the drawings said
  • Assessed the cabling already in place and what could stay
  • Identified the pinch points where added cable would restrict airflow or exceed the tray capacity
  • Set the cable types and quantities from the equipment list rather than estimating

Phase two: plans before cable

Our design team produced floor maps and digital plans covering cable routes and management, the rack and equipment layout, the cable types and lengths with a labelling scheme, and the pathways left spare for the facility to expand into. Those plans were signed off before installation so the crew was building to a drawing, not improvising.

Phase three: fiber and Cat6

  • Fiber and Cat6 installed to the approved plans
  • Every run terminated and tested, with results recorded against the port it belongs to
  • Bundling, dressing and labelling done as part of the install rather than tidied up afterwards
  • Routing kept clear of airflow paths and within the containment capacity

Phase four: testing and as-builts

Every connection was tested for performance, checked against the standards the facility works to, and any discrepancy was corrected before sign-off. The client received as-built drawings, the full test results and the labelling scheme, so the facility’s own team can trace any circuit without calling us.

The result

The data centre went into service with a cabling plant that is documented end to end and has room designed in for the next expansion. For the IT company that hired us, the useful part was handing their own client a complete set of drawings and results rather than a folder of photos.

Related: structured cabling, fiber optic cabling, server room cabling and our guide to rack sizes and rack units.

Need a cabling subcontractor who documents the work?

We work directly for end clients and as a subcontractor to IT firms and general contractors across the GTA. Call 1-647-846-1925.